How Do You Read an Oil Well Completion Diagram?

Somebody just handed you a wellbore schematic before a job. It's a tall, skinny drawing covered in nested lines, little triangles, cross-hatching and depth numbers. Everybody else in the doghouse seems to read it in ten seconds. You need to read it too, and you need to read it right, because the job plan hangs on it. How do you read an oil well completion diagram?
You read an oil well completion diagram from the outside in and from the top down: first the casing strings and their cement, then the tubing and everything hung inside it, then the perforations and the bottom of the well. The drawing is a side view of the well, usually not to scale horizontally, with depths written along one side. Wide lines on the outside are the bigger, shallower casing strings, and each smaller string inside goes deeper.
Symbols mark key items like packers, nipples, safety valves, plugs and perforations, and a table beside the drawing lists each item's size, weight, grade and depth. Once you learn the handful of standard symbols, you can trace the full path from the reservoir to the wellhead.
What Is a Wellbore Schematic Showing You?
A wellbore schematic (also called a well diagram or completion schematic) is a simplified cross-section of the well. It shows what steel, cement and hardware sit at what depth.
It's not a picture of the hole's true path. A horizontal well might be drawn as a straight vertical line with a note about the lateral, or with a simple bend. The width is stretched so you can see every string, so don't try to measure clearances off the drawing.
Most schematics include three parts:
- The drawing itself, with the well shown as nested vertical lines.
- A depth column, usually measured depth (MD) and sometimes true vertical depth (TVD).
- An equipment table that lists each component, its outside and inside diameter, its connection, and its top and bottom depth.
How Do You Read a Completion Diagram Step by Step?
Here's the routine I'd use the first time I see a well's schematic. It catches most of the surprises before they catch you.
- Check the header. Confirm the well name, API number, date and whether the drawing is current. An old schematic is a trap.
- Note the datum. Depths are usually measured from the kelly bushing or rig floor of the drilling rig. Your workover rig floor may be at a different height.
- Trace the casing strings from outside in. Write down each size and setting depth: conductor, surface, intermediate, production casing or liner.
- Look at the cement. Shaded areas show where cement sits behind each string. Note the top of cement.
- Follow the tubing. Find where it lands in the wellhead, then work down through every item hung on it.
- Find the barriers. Mark the packer, any plugs and any safety valve. These are what hold pressure.
- Find the producing zones. Locate the perforations, screens or open hole and note the intervals.
- Check the bottom. Look for the plug-back depth, fill, a bridge plug or any noted fish or junk.
- Read the notes. The small print often holds the most important warnings, like a casing leak or a stuck tool.
A common misread: assuming the smallest restriction is the tubing ID. A landing nipple or a gauge mandrel is often the real tight spot, and that's what decides which tools can pass.
What Do the Completion Schematic Symbols Mean?
Completion schematic symbols are not fully standardized. Every operator and software package draws them a little differently. Still, most follow the same general look, and the equipment table always tells you what each symbol is.
| What you see | What it usually means |
|---|---|
| Pairs of thick vertical lines | Casing strings, getting smaller as they go deeper |
| Small triangle or "shoe" mark at the bottom of a string | Casing shoe (setting depth) |
| Shading or dots between casing and hole | Cement |
| Thin pair of lines in the center | Production tubing |
| Solid block or X pattern between tubing and casing | Packer |
| Short marks or dashes through the casing wall | Perforations |
| Small notch or ring in the tubing | Landing nipple or profile |
| Box labeled SSSV or SCSSV | Subsurface safety valve |
| Small offset pocket on the tubing | Side-pocket mandrel (often for gas lift) |
| Solid bar across the casing | Bridge plug or cement plug |
| Fine mesh or slotted lines | Screen or slotted liner |
When in doubt, read the label. If there's no label and no table entry, ask. Guessing on a schematic is how tools get stuck.
What Is the Difference Between MD and TVD on a Well Diagram?
Measured depth (MD) is the length of the hole along its path. True vertical depth (TVD) is how far straight down that point is from surface. In a vertical well they're nearly the same. In a deviated or horizontal well, MD can be far larger than TVD.
Use MD for anything you run in the hole, because tools travel along the wellbore. Use TVD for pressure calculations, because hydrostatic pressure depends on vertical height. Mixing them up is a classic error on kill sheets and job plans.
Who Uses an Oil Well Completion Diagram?
Pretty much everybody who touches the well after it's drilled. Engineers plan jobs from it. Rig crews use it to know what they're pulling. Wireline crews use it to pick tool sizes and to know where their tools might hang up.
If you work around wireline services, the schematic is the first thing you look at on every job. The smallest ID, the deviation and the location of every nipple decide whether the tool string makes it to depth and back.
Regulators and buyers use these drawings too. When a well changes hands, the schematic is one of the first records the new owner wants.
Where Do People Go Wrong Reading Well Diagrams?
Here are the warning signs that a schematic, or the way it's being read, is about to cause trouble:
- The date is old and there have been workovers since.
- Depths don't add up when you sum the component lengths.
- The datum isn't stated, or the elevation doesn't match your rig.
- Items appear on the drawing but not in the table, or the other way around.
- A note mentions "fish," "junk," "collapsed casing" or "tight spot" and nobody brought it up in the job meeting.
- The drawing shows a packer type, but the setting and release method isn't listed.
When you spot one of these, raise it before the job starts. The company man and the toolpusher make the call, but they can only make a good call with good information.
What Does a Typical Completion Look Like on Paper?
A common land well schematic, read from top to bottom, might look like this in words:

- Conductor pipe near surface, cemented to surface.
- Surface casing below the deepest freshwater zone, cemented to surface.
- Production casing to total depth, with a top of cement noted somewhere above the pay zone.
- Tubing hung from the tubing head, running down to a packer set above the perforations.
- A seating nipple near the bottom of the tubing, with a tubing tail below the packer.
- Perforated intervals across the pay zone.
- Plug-back depth and casing shoe at the bottom.
The SLB glossary entry on the packer is a good reference if that symbol keeps tripping you up, since packers are the piece most people misread.
Reading an Oil Well Completion Diagram: Outside In, Top Down
Reading an oil well completion diagram comes down to a routine: check the header and datum, trace the casing outside in, follow the tubing top down, find the barriers, find the pay, and read every note.
The symbols vary a bit by company, but the equipment table settles any doubt. Keep MD and TVD straight, and always find the tightest ID before you pick a tool.
Next time somebody hands you a schematic, walk through it out loud with the crew. You'll catch more problems on paper than you ever will downhole.